标题:The CESAW dataset: a conversation
查看原文 PDF 中文 PDF (下批处理) EasyResearch 阅读摘要:An analysis of the 61,817 tasks performed by developers working on 45 projects, implemented using Team Software Process, is documented via a conversation between a data analyst and the person who collected, compiled, and originally analyzed the data. Five projects were safety critical, containing a total of 28,899 tasks. Projects were broken down using a Work Breakdown Structure to create a hierarchical organization, with tasks at the leaf nodes. The WBS information enables task organization within a project to be investigated, e.g., how related tasks are sequenced together. Task data includes: kind of task, anonymous developer id, start/end time/date, as well as interruption and break times; a total of 203,621 time facts. Task effort estimation accuracy was found to be influenced by factors such as the person making the estimate, the project involved, and the propensity to use round numbers.