标题:The formula for the completion time of project networks

作者:Manuel Castejón-Limas, Gabriel Medina Martínez, Virginia Riego del Castillo, Laura Fernández-Robles
查看论文《The formula for the completion time of project networks》的 PDF
查看原文 PDF 中文 PDF (下批处理) EasyResearch 阅读
摘要:This paper formulates the completion time $\tau$ of a project network as $ \tau =\|\mathbf{R} \mathbf{t} \|_\infty $ where the rows of $\mathbf{R}$ are simple paths of the network and $\mathbf{t}$ is a column vector representing the duration of the activities. Considering this product as a linear transformation leads to interesting findings on the topological relevance of both paths and activities using singular value decomposition. The notion of spectral networks is introduced to condense the fundamental structure of the project network. A definition of project stress is introduced to establish a comparison index between two alternatives in terms of slack. Additionally, the Moore-Penrose inverse of $\mathbf{R}$ is presented to find the configuration of the durations of the activities resulting in a given simple path duration vector. Then, the systematic mapping review process carried out to assess our claims' novelty is reported. Finally, we reflect on the notion of relevance for paths and activities and the relationship of the incidence matrix with the proposed approach.
评论: 20 pages, 2 figures
主题: 离散数学 (cs.DM)
引用方式: arXiv:2410.10252 [cs.DM]
  (或者 arXiv:2410.10252v1 [cs.DM] 对于此版本)
  https://doi.org/10.48550/arXiv.2410.10252

提交历史

来自:Virginia Riego Del Castillo
[v1] 2024年10月14日 星期一 08:08:30 UTC
全文链接:

访问论文:

  • 查看原文 PDF
  • 中文 PDF (下批处理)
  • EasyResearch 阅读
  • TeX 源文件
  • arXiv 原文页面
查看许可

当前浏览上下文:

cs.DM
< 上一篇   |   下一篇 >
最新 | 近期 | 2024-10
切换浏览方式为:
cs

参考文献与引用

  • Google Scholar
  • Semantic Scholar

BibTeX 格式的引用

EasyXiv 是独立运营的中文预印本站点,与 arXiv 及康奈尔大学无隶属关系。 论文元数据与原文来自 arXiv.org,感谢 arXiv 提供开放获取服务。
关于 · 帮助 · 投稿指南 · 版权 · arXiv 原站