标题:Post-disaster Repair Scheduling in Partially Automated Electricity Distribution Networks
查看原文 PDF 中文 PDF (下批处理) EasyResearch 阅读摘要:Natural disasters require repairing all damaged components in electricity distribution networks. Optimal scheduling repair crews to minimize the aggregate duration of interruptions reduces the harm. We consider the fact that the number of switches is much smaller than the number of edges. The problem is modeled by a parallel identical machine scheduling with group soft precedence constraints to minimize the total weighted energization time. We propose an LP-based list scheduling algorithm and a conversion algorithm and analyze their theoretical performances.